The status of the project at the date of this claim period from 1 May to 1 June 2014 is as follows:
- Retaining walls and planters are 90% complete
- Stormwater drains are 95% complete
- Fire Services is 15% complete
- Cold Water Supply is 95% complete
- Pad footings are 98% complete
- Ground slab is 85% complete
- Third floor:
– Suspended slabs 60% complete
– Stairs 90% complete
- Precast panels:
– Third floor 55% complete
- Wall Framing:
– Ground Floor complete
– First Floor 65% complete
- Fire Doors:
– Basement complete
– Ground Floor 90% complete
- Windows:
– Ground floor 20% complete
- Waterproof membranes. 60% of basement complete
- Metalwork:
– Basement complete
– Ground Floor 20% complete
- Waterproof membranes 60% of basement complete
- Plasterboard:
– Basement complete
– Ground Floor 30% complete
– Hydraulics 33% complete
– Sprinklers 36% complete
– Mechanical 18% complete
– Electrical 34% complete