‘REYNOLDS GARDENS’ MAY 2014

The status of the project at the date of this claim period from 1 May to 1 June 2014 is as follows:

 

  • Retaining walls and planters are 90% complete
  • Stormwater drains are 95% complete
  • Fire Services is 15% complete
  • Cold Water Supply is 95% complete
  • Pad footings are 98% complete
  • Ground slab is 85% complete

 

  • Third floor:
    – Suspended slabs 60% complete
    – Stairs 90% complete

 

  • Precast panels:
    – Third floor 55% complete

 

  • Wall Framing:
    – Ground Floor complete
    – First Floor 65% complete

 

  • Fire Doors:
    – Basement complete
    – Ground Floor 90% complete

 

  • Windows:
    – Ground floor 20% complete

 

  • Waterproof membranes. 60% of basement complete

 

  • Metalwork:
    – Basement complete
    – Ground Floor 20% complete

 

  • Waterproof membranes 60% of basement complete

 

  • Plasterboard:
    – Basement complete
    – Ground Floor 30% complete
    – Hydraulics 33% complete
    – Sprinklers 36% complete
    – Mechanical 18% complete
    – Electrical 34% complete

 

 

 

 