‘REYNOLDS GARDENS’ JUNE 2014

The status of the project at the date of this claim period from 1 June to 1 July 2014 is as follows:

 

  • Concreter – 99% complete
  • Precast – 98% complete
  • Steelwork – 38% complete
  • Carpentry – 21% complete
  • Doors – 29% complete
  • Windows – 18% complete
  • Plasterboard – 26%
  • Hydraulics – 42% complete
  • Fire Service – 46% complete
  • Mechanical – 28% complete
  • Electrical – 46% complete

 

 

 

 