The status of the project at the date of this claim period from 1 June to 1 July 2014 is as follows:
- Concreter – 99% complete
- Precast – 98% complete
- Steelwork – 38% complete
- Carpentry – 21% complete
- Doors – 29% complete
- Windows – 18% complete
- Plasterboard – 26%
- Hydraulics – 42% complete
- Fire Service – 46% complete
- Mechanical – 28% complete
- Electrical – 46% complete