The status of the project at the date of this claim period from 1 July to 1 August 2014 is as follows:
- Concreter – 99% complete
- Precast – 100% complete
- Steelwork – 89% complete
- Carpentry – 34% complete
- Doors – 34% complete
- Windows – 33% complete
- Metalwork – 19% complete
- Plasterboard – 42% complete
- Hydraulics – 48% complete
- Fire Service – 50% complete
- Mechanical – 36% complete
- Electrical – 51% complete