‘REYNOLDS GARDENS’ FOR JULY 2014

The status of the project at the date of this claim period from 1 July to 1 August 2014 is as follows:

 

 

  • Concreter – 99% complete
  • Precast – 100% complete
  • Steelwork – 89% complete
  • Carpentry – 34% complete
  • Doors – 34% complete
  • Windows – 33% complete
  • Metalwork – 19% complete
  • Plasterboard – 42% complete
  • Hydraulics – 48% complete
  • Fire Service – 50% complete
  • Mechanical – 36% complete
  • Electrical – 51% complete

 

 

 

 