‘REYNOLDS GARDENS’ FOR AUG 2014

The status of the project at the date of this claim period from 1 August to 1 September 2014 is as follows:

 

 

  • Concreter – 99% complete
  • Steelwork – 100% complete
  • Carpentry – 52% complete
  • Doors – 64% complete
  • Windows – 49% complete
  • Metalwork – 20% complete
  • Plasterboard – 48% complete
  • Hydraulics – 53% complete
  • Fire Service – 74% complete
  • Mechanical – 49% complete
  • Electrical – 55% complete

 

 

 

 