‘MIDDLE BURKE’ 28 October 2015

The status of Middle Burke apartments is as follows:

 

  • Level 0 ground floor slab pour 2 is completed
  • Level 0 ground floor slab pour 3 has commenced
  • Level 1  southern floor slab has commenced

 

 