  • ‘MIDDLE BURKE’ 26 November 2015

    29 November 2015 , Construction Update

    The status of Middle Burke apartments is as follows: Level 1 Pour 2 is completed Level 2 poured by Christmas        

  • ‘MIDDLE BURKE’ 20 November 2015

    20 November 2015 , Construction Update

    The status of Middle Burke apartments is as follows:   Level 0 ground – Pour 4 is completed. Level 1  floor slab Pour 2 was commenced.                  

  • ‘MIDDLE BURKE’ 13 November 2015

    13 November 2015 , Construction Update

    The status of Middle Burke apartments is as follows:   Level 0 ground – Pour 4 was commenced. Level 1  floor slab Pour 1 is completed.                          

  • The Seasons! Spotlight in Domain

    8 November 2015 , General News

    The Seasons hot on Development Spotlight

  • ‘MIDDLE BURKE’ 4 November 2015

    7 November 2015 , Construction Update

    The status of Middle Burke apartments is as follows:   Level 0 ground floor slab concrete pouring is 80 percent completed. Level 1  southern floor slab pour 1 is commenced.