The Victoriana
-Piling on East, South and West side are finished.
-West side capping beam has finished.
-Piling on North side has commenced.

JD the Seasons
-Building 1 ground floor slab commencing.
-Building 4 basement floor slab commencing.
-The 3rd crane tower activated.