‘REYNOLDS GARDENS’ NOV 2014

The status of the project at the date of this claim period from 1 November to 1 December 2014 is as follows:

 

  • Carpentry – 88% complete
  • Doors – 87% complete
  • Windows – 94% complete
  • Joinery – 70% complete
  • Metalwork – 48% complete
  • Floor finishes – 37% complete
  • Render – 67% complete
  • Painting – 44% complete
  • Plasterboard – 98% complete
  • Hydraulics – 83% complete
  • Fire Service – 98% complete
  • Mechanical – 80% complete
  • Electrical – 82% complete
  • Lifts – 99% complete

 

 