The status of the project at the date of this claim period from 1 November to 1 December 2014 is as follows:
- Carpentry – 88% complete
- Doors – 87% complete
- Windows – 94% complete
- Joinery – 70% complete
- Metalwork – 48% complete
- Floor finishes – 37% complete
- Render – 67% complete
- Painting – 44% complete
- Plasterboard – 98% complete
- Hydraulics – 83% complete
- Fire Service – 98% complete
- Mechanical – 80% complete
- Electrical – 82% complete
- Lifts – 99% complete