‘REYNOLDS GARDENS’ SEP 2014

The status of the project at the date of this claim period from 1 September to 1 October 2014 is as follows:

 

  • Concreter – 100% complete
  • Carpentry – 64% complete
  • Doors – 66% complete
  • Windows – 65% complete
  • Metalwork – 25% complete
  • Plasterboard – 67% complete
  • Hydraulics – 61% complete
  • Fire Service – 81% complete
  • Mechanical – 64% complete
  • Electrical – 62% complete
  • Lift – 75% complete

 

 

 