‘MIDDLE BURKE’ 29 July 2016

The status of Middle Burke apartments is as follows:

 

  • Basement wet wall rendering continuing.
  • Level 1 – plasterboard sheeting finished
  • Level 2 & 3 plasterboard sheeting continuing
  • Level 1 – water proofing finished, tiling continuing
  • Level 2 & 3 – Waterproofing continuing, tiling commenced
  • Level 1, 2 – carbineting partly finished.

 