The status of the project at the date of this claim period from 1 October to 1 November 2014 is as follows:
- Carpentry – 76% complete
- Doors – 72% complete
- Windows – 84% complete
- Joinery – 46% complete
- Metalwork – 31% complete
- Floor finishes – 27% complete
- Render – 52% complete
- Painting – 40% complete
- Plasterboard – 87% complete
- Hydraulics – 75% complete
- Fire Service – 98% complete
- Mechanical – 80% complete
- Electrical – 74% complete
- Lift – 99% complete