‘REYNOLDS GARDENS’ OCT 2014

The status of the project at the date of this claim period from 1 October to 1 November 2014 is as follows:

 

  • Carpentry – 76% complete
  • Doors – 72% complete
  • Windows – 84% complete
  • Joinery – 46% complete
  • Metalwork – 31% complete
  • Floor finishes – 27% complete
  • Render – 52% complete
  • Painting – 40% complete
  • Plasterboard – 87% complete
  • Hydraulics – 75% complete
  • Fire Service – 98% complete
  • Mechanical – 80% complete
  • Electrical – 74% complete
  • Lift – 99% complete

 

 