‘REYNOLDS GARDENS’ JAN 2015

The status of the project at the date of this claim period from 15 December 2014 to 1 February 2015 is as follows:

 

 

  • Carpentry – 95% complete
  • Windows – 98% complete
  • Joinery – 75% complete
  • Metalwork – 68% complete
  • Floor finishes – 59% complete
  • Render – 87% complete
  • Painting – 68% complete
  • Hydraulics – 92% complete
  • Fire Service – 99% complete
  • Mechanical – 92% complete
  • Electrical – 91% complete
  • Lifts – 99% complete

 

This project is expected to be settled by May 2015.

 