The status of the project at the date of this claim period from 15 December 2014 to 1 February 2015 is as follows:
- Carpentry – 95% complete
- Windows – 98% complete
- Joinery – 75% complete
- Metalwork – 68% complete
- Floor finishes – 59% complete
- Render – 87% complete
- Painting – 68% complete
- Hydraulics – 92% complete
- Fire Service – 99% complete
- Mechanical – 92% complete
- Electrical – 91% complete
- Lifts – 99% complete
This project is expected to be settled by May 2015.