‘REYNOLDS GARDENS’ FEB 2015

The status of the project at the date of this claim period from 1 February 2015 to 1 March is as follows:

 

 

  • Carpentry – 97% complete
  • Windows – 98% complete
  • Joinery – 89% complete
  • Metalwork – 83% complete
  • Floor finishes – 81% complete
  • Render – 89% complete
  • Painting – 78% complete
  • Hydraulics – 94% complete
  • Fire Service – 100% complete
  • Mechanical – 95% complete
  • Electrical – 94% complete
  • Lifts – 99% complete

 