The status of the project at the date of this claim period from 1 February 2015 to 1 March is as follows:
- Carpentry – 97% complete
- Windows – 98% complete
- Joinery – 89% complete
- Metalwork – 83% complete
- Floor finishes – 81% complete
- Render – 89% complete
- Painting – 78% complete
- Hydraulics – 94% complete
- Fire Service – 100% complete
- Mechanical – 95% complete
- Electrical – 94% complete
- Lifts – 99% complete